Sheraton Hotel SomaBay
Project

Sheraton Hotel SomaBay

Gallery

Project Images

Build Progression

Project Timeline

Dec 2023 – Oct 2025 Completed
Dec 2023 to mid 2024
Structure
Mid 2024 to early 2025
MEP and fit out
Early 2025 to Oct 2025
Finishing and handover
Overview

About This Project

Duration
Ongoing
2023-12-03 — Present
Consultant
ACE
Owner
SomaBay

Sheraton does not hand its name to just anyone. Across four builds along the same stretch of Soma Bay coastline, Multi Solutions Construction has delivered 159 guest rooms across two extensions, is bringing 14 beachfront chalets and 30 VIP villas up to five star standard, and has broken ground on a dedicated sports facility — each carried through the same disciplined process of new blockwork, full MEP, plaster, painting, gypsum ceilings, wood works, and marble and porcelain finishes, floor by floor, room by room.

Project Scope
159 Guest Rooms (98 + 61 across two phases)
14 Beachfront Chalets
30 VIP Villas
Dedicated Sports Shed facility
New blockwork, full MEP, plaster, painting, gypsum ceilings, wood works, marble and porcelain finishes